Match symptoms to checks
Record where the problem starts, when it appears and which roll was in use. Then choose a measurement that can help explain the failure and an observation that can show whether a change improves the package.
| What you observe | First check | Verify on the load |
|---|---|---|
| A hole starts at a corner or protrusion | Probe puncture under matched conditions | Use the actual corner, photograph the first damage and record how many repeat wraps show it. |
| Film narrows, splits or breaks as it is applied | Working stretch, applied width and starting defect | Record the point in the wrap cycle and inspect coverage and overlap at that position. |
| The tail peels away after wrapping | Peel cling with the actual film faces identified | Check mounting direction and inspect the tail immediately and after the handling interval. |
| The load loosens during storage | Stress relaxation and load settling | Recheck the same top, middle and bottom positions at the times agreed for the trial. |
Separate material and process
Identify the film by sample and lot and record width, thickness, storage and roll condition. For the process, record the load pattern, machine or hand method, settings, overlap, corner protection and operator. Photograph the tear or gap before disturbing the load.
For example, if two rolls are compared after the carriage program was also changed, record a combined trial. To isolate the film effect, repeat with the same load and program where the process permits.
Read a performance sheet
Keep the value, unit, method and revision, sample ID, thickness, direction and conditioning on the same line. For film-to-film tests, specify the faces that touched. Mark an omitted field as not supplied so a reviewer can tell why a comparison is incomplete.
A tensile value in the machine direction can answer a directional material question. A held pallet requires a separate observation under the approved wrap program.
Choose the next test
Copy this checklist into the trial record and complete one row per sample and load combination.
- State the primary failure and agree what will count as a pass.
- Choose one sample measurement that relates to the failure and record its conditions.
- Wrap the reference load and log consumption, interruptions and observations.
- Recheck after the agreed interval and record whether this load and program are approved.
Use the stretch film test plan to assign the checks and set the decision rule before samples are run.
Download the trial record (CSV)